Building Permits in Toronto: How Long They Take and What Slows Them Down

By Suren Varatharajan, Vanguard Build Limited ·

“How long will the permit take?” is the first scheduling question almost every client asks us. The official answer is short. The real answer depends on how ready your application is when it goes in. Here are both, from a contractor who files permits with the City of Toronto regularly.

The Official Timelines

Toronto Building sorts permit applications into review streams, and each one has a target time for a complete application:

Those numbers are real, but notice the word complete. That’s where most of the waiting happens.

What “Complete” Means, and Why It Matters

The City treats an application as complete only once all the required pieces are in. For most projects that includes an issued Zoning Applicable Law Certificate (ZAP), which confirms your plans comply with the zoning by-law and other applicable law. Without it, the City considers the application incomplete, and there is no review time limit for incomplete applications.

In practice, the 10-day clock doesn’t start the day you hand in drawings. It starts when the City has everything it needs.

A Real Example: 8 Months Stuck, Then 2 Weeks to Approval

A homeowner came to us after their permit application for a garage addition had been sitting with the City of Toronto for about eight months, with no clear end date. They were simply waiting for the City to move.

Once we were retained, we stopped waiting. We went back to the City and asked directly what was missing from the application, then worked closely with the designer to resolve each item properly rather than patching it. With the gaps closed and the application complete, the permit was issued in about two weeks, and we started construction right away.

See the photos and the full story: Bendale detached garage project.

Nothing about the project changed. What changed was that someone who knows the process chased the right questions and made sure the application was complete.

What Actually Slows a Permit Down

  1. Zoning problems. If the design exceeds what zoning allows (height, setbacks, lot coverage, floor area), you can’t simply submit and wait. You either redesign to comply, or apply for a minor variance through the Committee of Adjustment, a separate process with its own hearing that can add significant time.
  2. Incomplete or unclear drawings. Missing dimensions, no current survey, or plans that don’t match the site lead to revisions. Each round of comments and resubmission adds time.
  3. Structural changes without engineering. Removing a load-bearing wall, adding a second storey or cutting a new opening needs engineered details. If those come in late, the review stalls.
  4. Other approvals. Depending on the property, heritage, ravine, tree or other rules can apply and need sign-off before the permit is issued.
  5. Nobody following up. As the example above shows, an application can sit for months when no one is actively asking what’s missing.
  6. Starting late. If you want to build in spring, the drawings should be underway in winter.

Do You Even Need a Permit?

Not every renovation does. Cosmetic work in the same layout (new cabinets, counters, flooring, paint) usually doesn’t. You usually do need one for:

If you’re not sure, ask before work starts. Building without a required permit can mean stop-work orders, opening up finished work for inspection, and problems when you sell or make an insurance claim.

How We Keep Permits Moving

The Bottom Line

A complete house permit can be reviewed in about two weeks. An incomplete one can sit for months. The difference is almost entirely preparation and follow-up.